405 Project Delays & Costs: So Who's Paying?

Posted: Updated:
Los Angeles, CA -

You've heard the bad news, the 405 freeway widening project through The Sepulveda pass will take another year and 100 million bucks more than planned.

So who is going to pay for the cost overruns?

From April 25th story:

(FOX 11 / AP) Los Angeles motorists are accustomed to waiting in traffic on Interstate 405. Now they'll have an even longer wait for construction to be completed on the key north-south artery.

The ongoing project to widen one of the nation's busiest freeways will take a year longer than initially planned, and the price tag will jump about $100 million beyond the initial $1 billion figure, the Los Angeles Times reported Wednesday.

Several factors have contributed to the cost overruns and delays, including the structural failure of miles of sound walls, a legal fight over the placement of ramps, and the logistics of relocating utility lines, the newspaper said.

"This project has been horribly managed," said Los Angeles County Supervisor Zev Yaroslavsky, pointing the finger at the main contractor, Kiewit Infrastructure West Co., and subcontractors. "They've shown a complete lack of sensitivity and empathy for the community in which they're doing the work."

Kiewit defended its work.

"The costs and schedule impacts are the result of the project's overall complexity and the significant challenges associated with multiple unexpected utility and right of way issues," the company said. "Kiewit and Metro are committed to working together to minimize future delays and resolve final costs."

Metropolitan Transportation Authority officials agreed that some of the problems, such as the utility lines and ramps, were out of the contractor's control.

Transportation officials now say they hope to complete the bulk of the project by June 2014, with some of the work around traffic-clogged Sunset Boulevard lasting perhaps into the fall of that year.

The project was first forecast to be done this spring, and the date was later pushed back to December.

Preliminary work on the final 10-mile leg of a carpool lane through the Sepulveda Pass began four years ago. In addition to completing the northbound carpool link between Orange County and the San Fernando Valley, the project called for new ramps, rebuilding three bridges and adding miles of retaining and sound walls.

One frustrated commuter has even put $50,000 of his own money to get the project moving more quickly - but there's little to show for it.

Elon Musk, who co-founded PayPal and Tesla Motors Inc., says it's easier getting rockets into orbit than driving between his Bel-Air home and his Space Exploration Technologies factory in Hawthorne.

"The 405 ... varies from bad to horrendous," Musk told the newspaper.

The ambitious project has required two temporary weekend closures of the busy freeway - one last year and another in 2011 - that became known as Carmageddon I and II.

  • Share ThisMore>>

  • Anaheim's Wonderful WonderCon

    Anaheim's Wonderful WonderCon

    Saturday, April 19 2014 9:01 PM EDT2014-04-20 01:01:06 GMT
    It's Easter weekend and while some may be spending their time at Mass, there is a group of passionate people showing up in mass to celebrate their favorite superheroes at the Anaheim WondeCon.
    It's Easter weekend and while some may be spending their time at Mass, there is a group of passionate people showing up in mass to celebrate their favorite superheroes at the Anaheim WondeCon.
  • Kidnapping "Prank" Goes Bad, Parents Not Amused

    Kidnapping "Prank" Goes Bad, Parents Not Amused

    Friday, April 18 2014 1:58 PM EDT2014-04-18 17:58:38 GMT
    Twins brothers with a YouTube channel filled with their pranks say they weren't trying to make a joke. Serious intentions or not, a park full of parents were not amused by their latest stunt. This video is a must-see!
    Twins brothers with a YouTube channel filled with their pranks say they weren't trying to make a joke. Serious intentions or not, a park full of parents were not amused by their latest stunt. This video is a must-see!
  • Griffith Park Mountain Lion Found Sick, Possibly Poisoned

    Griffith Park Mountain Lion Found Sick, Possibly Poisoned

    Thursday, April 17 2014 3:26 PM EDT2014-04-17 19:26:14 GMT
    Rat poison may be responsible for the sorry condition of a wild mountain lion in LA's Griffith Park. The mountain lion is known to the National Park Service as ‘P-22'.
    Rat poison may be responsible for the sorry condition of a wild mountain lion in LA's Griffith Park. The mountain lion is known to the National Park Service as ‘P-22'.
Powered by WorldNow

KMSP-TV
11358 Viking Drive
Eden Prairie, MN 55344

Phone: (952) 944-9999
Fax: (952) 942-0455

Didn't find what you were looking for?
All content © Copyright 2000 - 2014 Fox Television Stations, Inc. and Worldnow. All Rights Reserved.
Privacy Policy | Terms of Service | Ad Choices